Colombia’s Superintendencia Financiera has warned insurers handling claims from the 10 August earthquake that unnecessary requirements and delays may trigger sanctions, including loss of authorisation to operate in the affected insurance line.
The payment deadline
The Superintendencia Financiera de Colombia said insurers have one month to pay an indemnity once the claimant’s right to payment has been established. The regulator’s warning addresses a point that can arise in any claims process: an internal step by the insurer does not automatically change the period for performance. In this case, the SFC said that waiting for an adjuster’s report does not extend the payment deadline. The rule places the focus on whether the right to indemnity has been established, rather than on whether every part of the insurer’s assessment process has been completed.
Requirements the regulator rejects
The SFC described asking for papers unrelated to the insured event as an abusive practice. It also said that an act of assembly deciding whether a building or residential complex will be rebuilt cannot be made a condition for paying damage to common property. These examples show the distinction between information relevant to a claim and formalities that may obstruct it. The warning does not remove an insurer’s ability to assess loss or verify a claim. It says that additional requirements must not be used to avoid or delay obligations under the insurance contract.
Sanctions and the wider lesson
The regulator said unjustified obstacles may lead to sanctions and, in cases provided for by law, may cost a company its authorisation to operate in the insurance line where the conduct is detected. The announcement is a regulatory warning, not a finding that every insurer handling earthquake claims has breached the rules. For organisations managing insured buildings or other assets, the transferable point is procedural: a claim should be assessed against the event and the insured right, while steps that do not establish that right should not be allowed to extend the payment period. The SFC’s intervention keeps that boundary in view.
| Fact | Detail |
|---|---|
| Regulator | Superintendencia Financiera de Colombia |
| Event | The earthquake of 10 August |
| Payment period | One month after the right to indemnity is established |
| Adjuster’s report | Waiting for it does not extend the payment deadline |
| Common property | An assembly act on rebuilding cannot be a condition for indemnifying damage |
| Possible consequence | Revocation of authorisation to operate the affected insurance line, in cases provided by law |
Waiting for the report of the adjuster does not extend the deadline to pay.
WHY IT MATTERS
The warning clarifies how a regulated payment process should work: once the insured right is established, administrative or assessment steps that do not determine that right should not be used to postpone payment. Unjustified obstacles can expose insurers to sanctions.